News from The Boardroom-September 2016 (2)

   Horncliffe – I’m afraid there is a further delay as the Environment Agency have changed the original arrangements whereby they were doing the rebuilding of the embankment. A contractor has now been appointed and we are liaising with them. Unfortunately the costs have gone up by a further £10,000 from £36,000 to £46,000. LCC have … More News from The Boardroom-September 2016 (2)

Burrs New Station Update

Work in laying out the new access up to the platform is complete. The fencing around the platform is also complete. Tarmac to the access path has commenced today (5 Oct) and will take a couple of days. On this photo a train is going through the station